Strengthening and Rehabilitation of U-Shaped RC Bridges Using Substitute Cable Ducts

Loading...
Thumbnail Image

Authors

Svoboda, Adam
Klusáček, Ladislav
Olšák, Martin

Advisor

Referee

Mark

Journal Title

Journal ISSN

Volume Title

Publisher

Hindawi Limited
Altmetrics

Abstract

The presented paper deals with strengthening and rehabilitation of U-shaped reinforced concrete bridges from the period of 1905–1930 using post-tensioning, which is a suitable, reliable, and durable method. These bridges have two main beams pulled over the bridge deck, which is supported by cross girders. The cross girders connect the two main beams forming a half-frame in the transverse direction, which provides spatial rigidity to the structure. The spans of these bridges are usually between 15 and 25m. The high efficiency of post-tensioning can be seen on many implemented applications for bridge reconstructions worldwide. However, in this paper, the post-tensioning method is extended by a unique structural system of substitute cable ducts that allows for significantly expanding applicability of this method on existing concrete bridges. This method is highly recommended due to minimization of interventions into the constructions, unseen method of cable arrangement, and hence the absence of impact on appearance, which is appreciated not only in case of valuable historical structures but in general as well. In conclusion, the post-tensioning by monostrands in substitute cable ducts is a highly efficient method for strengthening of existing bridges in order to increase their load-bearing capacities in terms of current traffic load and to extend their service life. This method was also verified by monitoring the behavior of rehabilitated bridges before and after strengthening.
The presented paper deals with strengthening and rehabilitation of U-shaped reinforced concrete bridges from the period of 1905–1930 using post-tensioning, which is a suitable, reliable, and durable method. These bridges have two main beams pulled over the bridge deck, which is supported by cross girders. The cross girders connect the two main beams forming a half-frame in the transverse direction, which provides spatial rigidity to the structure. The spans of these bridges are usually between 15 and 25m. The high efficiency of post-tensioning can be seen on many implemented applications for bridge reconstructions worldwide. However, in this paper, the post-tensioning method is extended by a unique structural system of substitute cable ducts that allows for significantly expanding applicability of this method on existing concrete bridges. This method is highly recommended due to minimization of interventions into the constructions, unseen method of cable arrangement, and hence the absence of impact on appearance, which is appreciated not only in case of valuable historical structures but in general as well. In conclusion, the post-tensioning by monostrands in substitute cable ducts is a highly efficient method for strengthening of existing bridges in order to increase their load-bearing capacities in terms of current traffic load and to extend their service life. This method was also verified by monitoring the behavior of rehabilitated bridges before and after strengthening.

Description

Citation

Advances in Materials Science and Engineering. 2019, vol. 2019, issue 8920718, p. 1-21.
https://www.hindawi.com/journals/amse/2019/8920718/

Document type

Peer-reviewed

Document version

Published version

Date of access to the full text

Language of document

en

Study field

Comittee

Date of acceptance

Defence

Result of defence

Endorsement

Review

Supplemented By

Referenced By

Creative Commons license

Except where otherwised noted, this item's license is described as Creative Commons Attribution 4.0 International
Citace PRO